Below is a summarized version of the Permanent Building Committee meeting, organized by timestamps and speakers, focusing on key points raised during the discussion in Reading, Massachusetts. This summary condenses the discussion into major themes, speaker contributions, and decisions, avoiding excessive detail while retaining the essence of the conversation. Timestamps correspond to the video linked at the bottom.
- π Summary
- π Agenda Overview
- π£οΈ Public Comment
- β Meeting Minutes Approved
- π’ Administrator / Manager Report
- π³ Discussion & Vote β Alternate No. 1: Range Road Extension
- π³ Discussion & Vote β Alternate No. 2: Photovoltaic System
- π³ Discussion & Vote β Acceptance of Additional Project Alternate
- π³ Discussion & Vote β Award of General Contractor
- π Community Spotlight
- π’ Administrator / Manager Report
- π³ Discussion & Vote β Project Invoices
- π Future Agenda Items
- π Key Summary
π February 11, 2026 Permanent Building Committee Meeting
π Meeting Start: 00:00:07
β° Meeting End: 01:45:26
π» Format: Pleasant Street Center and Zoom
π€ Chair: Patrick Tompkins
π₯ Attendees: Patrick Tompkins, Nancy Twomey (Vice Chair), John Coote, Kirk McCormick, Gregory Stepler, Mark L Dockser, Ronald Powell
π₯ Associates Present: Ari Greenberg, Kenneth Grizzell, Michael Nazzaro
π€ Staff / Consultants: Joe Huggins (Director of Facilities), Peter Collins Ownerβs Project Manager (OPM), BH+A representatives
π Summary
The Permanent Building Committee met to advance major procurement and construction milestones for the ReCAL project. The Committee reviewed the project schedule and budget, confirmed continued compliance with the voter-approved funding cap, and evaluated filed sub-bids, general contractor bids, and multiple project alternates.
Over the course of the meeting, the Committee approved prior meeting minutes, voted to accept key project alternates, and formally awarded the general construction contract to the lowest responsible and eligible bidder. Additional actions included approval of project invoices, receipt of ADA accessibility peer review findings, updates on upcoming procurements, and discussion of future meeting logistics.
π Agenda Overview
| β° Start Time | Topic |
|---|---|
| 00:00:07 | Call to Order & Roll Call |
| 00:03:10 | Public Comment |
| 00:03:28 | Meeting Minutes |
| 00:04:18 | Schedule & Budget Update |
| 00:07:12 | Filed Sub-Bids & General Bids Review |
| 00:34:22 | Vote β Alternate No. 1 (Range Road Extension) |
| 00:38:22 | Vote β Alternate No. 2 (Photovoltaic System) |
| 01:15:05 | Budget Context & Additional Alternate Discussion |
| 01:20:53 | Award of General Contractor |
| 01:24:07 | OPM Updates & ADA Review |
| 01:38:10 | Project Invoices |
| 01:41:14 | Future Meetings & Scheduling |
| 01:45:02 | Adjournment |
π£οΈ Public Comment
β° 00:03:10 β 00:03:28
π€ Presenter(s): None
No in-person or remote public comment.
β Meeting Minutes Approved
β° 00:03:28 β 00:04:15
π€ Presenter(s): Patrick Tompkins
January 7, 2026 Minutes: Approved as presented.
Vote: Unanimous.
π’ Administrator / Manager Report
β° 00:04:18 β 00:07:10
π€ Presenter(s): Peter Collins (Ownerβs Project Manager)
π Transportation / Infrastructure
- Project schedule remains on track.
- Contract execution targeted by late February 2026.
- Notice to Proceed anticipated in early March 2026.
πΌ Financial / Budget Status
- Overall project budget remains at $27.9 million.
- Approximately $2.7 million committed at the time of the report.
- Filed bids reviewed but not yet incorporated pending award.
- Contingency levels reviewed and confirmed.
π³ Discussion & Vote β Alternate No. 1: Range Road Extension
β° 00:34:22 β 00:38:12
π€ Presenter(s): Patrick Tompkins
Overview
Alternate No. 1 proposed extending Range Road to improve access and circulation for the ReCAL site and adjacent recreational facilities.
Key Discussion Points
- Improved traffic flow and site access.
- Supports overflow parking and coordination with adjacent uses.
- Pricing reviewed as competitive and consistent.
- Costs accommodated within the overall project budget.
Vote
β
Approved
Vote Count: 7β0β0
π³ Discussion & Vote β Alternate No. 2: Photovoltaic System
β° 00:38:22 β 01:15:05
π€ Presenter(s): Patrick Tompkins, BH+A design team
Overview
Alternate No. 2 proposed installation of a 100 kW rooftop photovoltaic system as part of the base construction.
Key Discussion Points
- Estimated 23-year nominal payback at current RMLD rates.
- Potential RMLD grant of up to $60,000 could reduce payback period.
- Alignment with Town Net Zero Action Plan and sustainability goals.
- Installation during construction avoids higher retrofit costs.
- Recognized long-term environmental and educational benefits.
Vote
β
Approved
Vote Count: Unanimous
π³ Discussion & Vote β Acceptance of Additional Project Alternate
β° 01:15:05 β 01:20:44
π€ Presenter(s): Patrick Tompkins
Overview
The Committee considered acceptance of an additional project alternate while emphasizing continued compliance with the voter-approved budget.
Key Discussion Points
- Project remains under the approved funding cap.
- Alternates were anticipated if savings allowed.
- Clarification requested on subcontractor bid ranking procedures.
Vote
β
Approved
Vote Count: 6β1
- No: John Coote
π³ Discussion & Vote β Award of General Contractor
β° 01:20:53 β 01:22:54
π€ Presenter(s): Patrick Tompkins
Overview
The Committee voted to award the general construction contract to the lowest responsible and eligible bidder.
Key Discussion Points
- Contractor held valid certificate of eligibility.
- Contractor pre-qualified and reviewed as responsible.
- Award independent of alternates accepted.
Vote
β
Approved
Vote Count: 7β0
π Community Spotlight
β° 01:23:02 β 01:24:05
π€ Presenter(s): Patrick Tompkins
The Chair recognized the awarding of the construction contract as a major project milestone and thanked BH+A, the OPM team, and project partners.
π’ Administrator / Manager Report
β° 01:24:07 β 01:31:10
π€ Presenter(s): Peter Collins (Ownerβs Project Manager)
π Transportation / Infrastructure
- Procurement for materials testing and inspectional services advertised.
- Six proposals received from ten solicited firms.
- Recommendation to be brought to a future meeting.
π State / Regional Policy (ADA Compliance)
- ADA peer review conducted by KMA Architects.
- 18-page report with 51 items, primarily clarifications.
- No significant scope or cost impacts identified.
- Minor adjustments to be issued via construction bulletin.
π³ Discussion & Vote β Project Invoices
β° 01:38:10 β 01:41:01
π€ Presenter(s): Peter Collins (Ownerβs Project Manager)
Invoices Approved
- BSCES (#27854): $60,000
- KJN00467: $24,377
- Invoice #484: $1,150
- KMA Architects (#17481): $4,700
- Times Chronicle Advertising (#60063): $35.50
Vote
β
All invoices approved
Vote Count: 7β0 on each vote
π Future Agenda Items
β° 01:41:14 β 01:45:02
π€ Presenter(s): Patrick Tompkins
- Upcoming meetings scheduled for March 4, April 1, and May 6.
- April meeting date may shift due to Passover, with April 15 discussed.
- Contractor meet-and-greet to be considered at a future meeting.
π Key Summary
- Project schedule and $27.9 million budget were reaffirmed as on track.
- January 7, 2026 meeting minutes were unanimously approved.
- Multiple project alternates, including Range Road Extension and rooftop photovoltaics, were approved.
- The general construction contract was unanimously awarded to the lowest responsible and eligible bidder.
- ADA peer review identified no significant design or cost impacts.
- Several project invoices were unanimously approved.
- Upcoming procurements and future meeting dates were reviewed.


